Light at the End of the Tunnel

01/03/2022 02:53:34 PM

Jan3

The sanctuary seating risers have been installed! The sanctuary wood wainscoting and fin tube radiator enclosures have been installed! Bathroom partitions and tile is in! It seems like this is almost, maybe, starting to kind of approach the home stretch.

Lots of other progress is ongoing. The final windows are being installed, the Rutherford entrance is taking shape and concrete exterior retaining walls, paths, and stairways are happening. Carpeting is being installed in assorted spaces throughout the building. The whole interior is being painted, and electrical and alarm devices are being put in.

In the next two weeks, the exterior concrete work will continue and the parking lot will be regraded. Window sills, sanctuary seating, lower level flooring, and the bimah should be in progress, along with millwork built-ins, and spaces will continue to be painted.