As of this week, the steel framing, sheathing, and roofing for the new sanctuary have been installed and the new roofing for the lobby has been completed. Classroom and office windows and door frames have been installed, and the exterior concrete walls and foundations for the stairs and ramp at the Rutherford entrance—what will be the main entrance—are in place. Mechanical rooftop units have been installed and plumbing, electrical and data wiring are still in progress, as is the exterior stucco application. New framing for the lobby stairs and railings is continuing.

In the next two weeks we can look forward to seeing windows in the sanctuary and drywall in the bathrooms and kitchen. Spray foam insulation will be blown into ducts above the sanctuary ceiling, along with the continuation of the sprinkler installation.