Mechanical & Electrical: Disconnection Continues

10/20/2020 09:49:26 AM

Oct20

This week general demolition and the disconnection of existing mechanical and electrical infrastructure continues. Final asbestos abatement is proceeding since ceilings and some interior walls have been demolished; it should wrap up soon. The workers have started the temporary shoring up of the exterior walls, and the contractor has submitted plumbing fixtures and stone samples to the architects and the HI renovation committee for review. In the next couple of weeks the existing south/west structure will be demolished and removed, excavation will begin, and the wall-framing for the bathrooms and kitchen on the upper floor will begin. Exciting!